期刊文献+

山阴县泥河水厂工程高压区供水管水锤分析研究

Analysis of water hammer in water supply pipeline of high pressure area in Nihe Waterworks engineering of Shanyin County
下载PDF
导出
摘要 针对供水工程高压区输水管道距离长、口径大、管道沿线地形起伏变化复杂,一旦发生停泵水锤现象,对输水管道乃至送水泵房破坏影响很大的问题,对泥河水厂高压区长距离大口径输水管道的水锤形成原因、危害及防护措施进行了分析和研究,以期提高供水系统的安全性。 Aimed at the issues of long distance and large diameter of water transmission pipeline in high pressure area of water supply engineering, complicated terrain of pipeline side which had had influence for water transmission pipeline and water supply pump house when the pump-stopping water hammer was occurred, the analysis and research of formation reason, damage and protection measures of water hammer were conducted in water transmission pipeline with long distance and large diameter of high pressure area in Nihe Waterworks in order to improve the safety of water supply system in future.
作者 刘涛
出处 《供水技术》 2013年第3期41-44,共4页 Water Technology
关键词 水厂 高压区 供水管路 水锤分析 waterworks high pressure area water supply pipeline water hammer analysis
  • 相关文献

参考文献4

  • 1上海市政工程设计研究院.给水排水设计手册(第3册)[M].北京:中国建筑工业出版社,2004.
  • 2马世波,张健.长距离输水工程停泵水锤防护措施研究[J].人民长江,2009,40(1):85-86. 被引量:19
  • 3王利强.远距离输水工程停泵水锤综合防护措施浅析[A].2011全国给水排水技术信息网年会暨技术交流会[C].乌海,2011.
  • 4黄晖.水锤及管道系统计算分析与实践[M].北京:中国建筑工业出版社,2004.

二级参考文献3

共引文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部