期刊文献+

山地城市地下污水处理厂建设模式探索 被引量:7

Construction Mode of Underground Sewage Treatment Plant in Mountainous City
下载PDF
导出
摘要 依托国内外先进的地下污水处理厂建设理论基础和实践经验,对山地城市重庆地下污水处理厂建设模式进行探讨。重庆市主城地质条件好,在经济技术可行的条件下,可合理开发利用地下空间,适当选择地下或地上地下相结合的污水处理厂建设模式。在建设中,应采用合理工艺,满足污水和气体排放要求;充分利用地下空间,集约紧凑布局;地下与地上建设相结合,减小施工难度和运行动力消耗;结合城市地形地貌,丰富山地城市景观特色;污水处理厂与再生水厂适当合建,促进水资源循环利用,有效提升山地城市经济、社会、环境效益。 Based on relevant theory and implementation experience of the construction of underground sewage treatment plant at home and abroad, construction modes of underground sewage treatment plant in Chongqing, a mountainous city, are discussed. The geological condition in the main urban districts of Chongqing is quite good, so underground space can be reasonably developed and used and the properly combined construction mode of overground and underground sewage treatment plant can be adopted within the existing technology capability. Under construction, reasonable technology should be applied to meet the requirements of sewage and gaseous emission. Underground space should be fully exploited to compact the layout, over- ground construction and underground construction should be combined to reduce construction difficulty and power consumption. Urban landscape should be taken into consideration to enrich city landscape. Sewage treatment plant and recycled water plant should be properly jointly built to foster the recycle of water resources and effectively promote the economic, social and environmental benefit of mountainous city.
出处 《重庆建筑》 2013年第6期3-6,共4页 Chongqing Architecture
关键词 山地城市 地下 污水处理厂 城市规划 mountainous city underground sewage treatment plant city planning
  • 相关文献

参考文献3

二级参考文献14

  • 1香港特别行政区渠务署.赤柱污水处理厂[R].,2002.5.
  • 2Birger Jansson. Water and sewage in caverns and tunnels: thirty years experience in sweden. Underground space[J] , vol.4. No. 1.Pp47 - 51,1989.
  • 3Lr.a.m.meskets, the dokhaven: an underground plant for sewage treatment in rotterdam, Underground space[J], vol.8 no. 1 1984 ,p18 - 23.
  • 4F. medbo and f. loser. Subsurface location of a major water pollution control plant presently under construction in the oalo area. Norwegian hard rock tunneling[J]. Norwegian soil and reek engineering assoeiaton. Publication no. 1.55 - 60.
  • 5Gsaetersmoen,consulting cngincer,Undergroud water treatment plant and reaervoirs in solo.Norwegian hard rock tunneling[J].Norwegian soil and rock engineering associaton,Publication no.1.81-82.
  • 6K.garshol. Excavation, support and pre- grouting of tbm - driven sewer tunnel. Norweging tunelling technology[J]. Norwegian soil and rock engineering association. Publication No.2.21 - 28.
  • 7K. garshol.Underground excavation and support of a major sewage.treatment plant for the aslo area.Norweging tunnelling technology [J].Norwegian soil rock engineering association.Publication No.2.45-49.
  • 8Gunnar asting,consulting cngincer,Expericnces with pregrouting in sewage tunnels in the oslo area.Norweging tunnelling technology [J].Norwegian soil and rock engineering association Publication No.2.57-64.
  • 9E.j.w.johansson&h.kuula. Thrce- dimensional back- analysis calculations of viiikinnaki underground sewage treatment plant in helsinki. International congress on rock mechanics[C], vol 2,597 -600, tokyo, japan, 1995.
  • 10Pavel uhcr, czechoslovakia's first underground sewage treatment plant, tunnelling and underground space technology[J], Vol.2 No.3,1987, p275 - 278.

共引文献36