资源不确定军事任务计划预测调度模型与算法 被引量:13

Method for modeling and solving military mission planning with uncertain resource availability
下载PDF
导出
摘要 针对军事任务计划执行环境中普遍存在的资源不确定性,提出了基于资源缓冲区的军事任务计划预测调度算法。算法首先基于平台有效资源功能向量进行任务—平台分配,分配过程中通过调节平台有效资源功能向量,获得不同的平台资源缓冲区分配方案;然后基于NSGA-Ⅱ算法框架对军事任务计划进行多目标求解,进而获得问题的Pareto最优解集。文章通过仿真算例对算法的可行性和有效性进行验证,实验结果表明,该算法能够有效求解资源不确定军事任务计划问题。 According to the ubiquitous uncertainty of resource availability,a multi-objective military mission planning model with uncertain resource availability is proposed based on reasonable hypotheses.A proactive schedule method based on resource buffer was designed according to the special features and particularity of the model.In the method,the resource buffer was added into the project during the task-platform allocation in order to minimize the disadvantage of resource uncertainty;the multi-objective evolutionary algorithm NSGA-Ⅱ was adopted to calculate the Pareto Front of the problem.Finally,an example was illustrated to show the feasibility and practicability of the proposed model and method.
出处 《国防科技大学学报》 EI CAS CSCD 北大核心 2013年第3期30-35,共6页 Journal of National University of Defense Technology
基金 国家自然科学基金资助项目(71201169 71101149 71001105 71031007) 湖南省自然科学基金资助项目(11JJ4065)
关键词 军事任务计划 作战行动序列 预测调度 资源缓冲区 military mission planning course of action proactive schedule resource buffer
  • 相关文献

参考文献9

  • 1Levchuk G M, Levchuk Y N, Luo J, et al. Normative design of organizations. I. Mission planning [J]. IEEE Transactions on Systems, Man and Cybernetics Part A: Systems and Humans ,2002, 32 (3) :346 - 359.
  • 2Belfares L, Klibi W, Lo N, et al. Multi-objectives tabu search based algorithm for progressive resource allocation [J]. European Journal of Operational Research, 2007, 177 ( 3 ) : 1779 - 1799.
  • 3Lambrechts O, Demeulemeester E, Herroelen W. Time slack- based techniques for robust project scheduling subject to resource uncertainty [J]. Annals of Operations Research, 2011, 186( 1 ) :443 -464.
  • 4Lambrechts O, Demeulemeester E, Herroelen W. Proaetive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities [J]. Journal of Scheduling,2008, 11 (2) :121 - 136.
  • 5Van de Vonder S, Demeulemeester E, Herroelen W. A classification of predictive-reactive project scheduling procedures [J]. Journal of Scheduling,2007, 10(3) : 195 -207.
  • 6Deb K, Pratap A, Agarwal S, et al. A fast and elitist muhiobjective genetic algorithm: NSGA-II[J]. IEEE Transactions on Evolutionary Computation, 2002, 6(2): 182-197.
  • 7Alcaraz J, Maroto C. A robust genetic algorithm for resource allocation in project sCheduling [J]. Annals of Operations Research,2001, 102( 1 ) :83 - 109.
  • 8Kleinman D, Young P, Higgins G. The DDD-III: A tool for empirical research in adaptive organizations [C]// Proceedings on Command and Control Research and Technology Symposium , 1996:827 -836.
  • 9Veldhuizen V. On mearsuring muhiobjective evolutionary algorithm performance [C]// Congress on evolutionary computation, 2000 : 204 - 211.

同被引文献78

引证文献13

二级引证文献98

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部