结合八一煤矿地面副井绞车主轴联轴器的更换过程 ,介绍了绞车联轴器更换方法 ,包括联轴器的拆除 ,新联轴器的装配及过盈配合孔件加热温度的计算方法。
The paper introduces the process of replacing the main shaft coupling on the service winding system at Bayi Coal Mine,the replacement method used,including dismounting of the old coupling,fitting of the new coupling,as well as the method for calculating the temperature required for heating the interference fit pieces.
出处
《水力采煤与管道运输》
2000年第3期33-34,48,共2页
Hydraulic Coal Mining & Pipeline Transportation