摘要
神皖安庆电厂2×320MW机组引风机增压风机合并改造方案,针对引风机选型、合并改造后的影响进行了论述,分析了合并后对锅炉的影响及所采取的措施,充分保证机组的安全性。结果证明300MW机组引风机增压风机合并改造并取消脱硫旁路是安全可行的。
This article briefly describes the merge and reconstruction scheme of Induced Draft Fan with Booster Fan in 2X300 MW Unit in Shenwan Anqing Power Plant. It discusses the selection of the induced draft fan and the influence of the merger to the boiler. It also analyzes the measures taken,fully guarantee the safety of the unit. It proves that the scheme of the combination and reconstruction of 300 MW Unit is feasible and safe.
出处
《节能》
2013年第6期28-31,2,共4页
Energy Conservation
关键词
引风机
增压风机
无旁路
induced draft fan
FGD booster fan
bypass