济三煤矿刮板输送机技术改造

Technical renovation of scraper conveyor in Jining No.3 colliery coal preparation plant
下载PDF
导出
摘要 为解决济三煤矿刮板输送机刮板和滑道工作面相互磨损,以及其在运行中出现故障无法及时监测的问题,结合生产实际对刮板输送机进行了滑道错位改造,并对其进行了分体式设计和拉斜保护设计。经技术改造和完善后刮板输送机运行稳定,故障率明显降低。 In order to solve the problems of wearing generated between the scraper conveyor and surface of the slide way, as well as detected the faults in a timely manner when the conveyor is running, based on the fact of production, making stagger position transform for slide way of the scraper conveyor and using the split type design and diagonal protection design. After the technical renovation and perfect, the running of the scraper conveyor is stable and significantly lowers the failure rate.
机构地区 济宁三号煤矿
出处 《选煤技术》 CAS 2013年第3期61-62,共2页 Coal Preparation Technology
关键词 磨损 滑道错位 拉斜保护 分体式设计 wearing slide way stagger position diagonal protection split type design
  • 相关文献

参考文献3

  • 1闻邦椿.振动机械理论及应用[M].北京:机械工业出版社,2009.
  • 2成大先.机械设计手册[M].北京:化学工业出版社,2002..
  • 3GB咒359—2005洗选工程设计规范[S].

共引文献909

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部