摘要
文章针对新安装汽轮发电机组轴系振动指标超标的质量通病,分析了振动产生的原因,探讨了安装阶段汽轮发电机组防轴系振动的控制要点,结合工程实例说明应用本文给出的控制措施,新装汽轮机组轴系振动可以达到机组168h满负荷试运行考核标准要求。
Based on common quality problems of vibration exceeding standard on the newly-installed steam turboset shaft, the cause of newly-installed unit shafting vibration is analyzed, and the main point to control the vibration is studied. Combined with engineering examples, research result indi- cates that the shafting vibration can meet the qualification during the 168h full load trial operation if the control measurements proposed in this paper are used
出处
《湖北电力》
2013年第3期62-64,67,共4页
Hubei Electric Power
关键词
汽轮发电机安装
轴系振动
轴系安装
steam generator erection
shafting vibration
shafting installation