摘要
以某碾压混凝土重力坝施工为例,采用有限元仿真的计算方法,就其度汛缺口过流坝段的温控防裂措施进行了详细分析。研究表明:缺口坝段过流前,采用仓面通河水流水养护并加上混凝土过流前中期冷却至一定温度是减小温差的有效措施,可在一定程度上防止裂缝的产生。这为今后碾压混凝土重力坝工程的建设提供一定的参考。
By taking the construction of a RCC gravity dam as the study case, a detailed analysis is made on the temperature control and anti-cracking measure for its dam section of the flood discharge gap. The study shows that curing the concrete placing face directly with the river water before the flood discharge and cooling the concrete to a certain temperature at the mid-term be- fore the discharge is an effective measure to decrease the relevant temperature difference; which can prevent the concrete cracking to a certain extent, and then provides a certain reference for the construction of RCC gravity dam in the days to come.
出处
《水利水电技术》
CSCD
北大核心
2013年第7期56-58,68,共4页
Water Resources and Hydropower Engineering
基金
国家"973"项目(2013CB036406
2013CB035903)
水利部公益性行业科研专项(201201050)
中国水利水电科学研究院科研专项(材集1208
材集1353
材集1361
材集1309)
国家"十二五"科技支撑项目(SQ2013BAJY4138)
关键词
碾压混凝土
重力坝
表面裂缝
度汛缺口
温控措施
roller compacted concrete
gravity dam
surface crack
flood discharge gap
temperature control measure