摘要
根据核电厂换料大修的特点,介绍大修经验反馈的可行性和必要性,同时按照时间节点,将大修经验反馈分成大修前、大修中和大修后3个阶段分别进行详细说明和讨论,并分别对其反馈方式、可行性等方面内容进行研究。最后总结了目前大修经验反馈工作中存在的主要问题和不足,并提出了改进方法的建议。
The necessity and feasibility of NPP refueling outage experience feedback are introduced in this paper.By time sequence,the process of outage experience feedback is divided into three parts for further discussion.With the result,the problems and deficiencies which are current existing are summarized,and the improvement suggestion is put forward.
出处
《核安全》
2013年第2期30-35,共6页
Nuclear Safety
关键词
核电厂
换料大修
经验反馈
nuclear power plant
refueling outage
experience feedback