从精度和工程要求出发,对太钢尖山铁矿新建溜井系统贯通测量方案进行了分析,总结了此次贯通测量的关键技术要点,提出了贯通过程中需注意的事项和保证精度的措施,以确保该系统的正常实施。
From the accuracy and engineering demands,the paper undertakes the analysis of the through survey plan of new jack shaft system of TISCO Jianshan iron ore,sums up the key technical points for the through plan,and points out some precautions and measures to ensure the accuracy in the through process,so as to ensure the common implementation of the system.
出处
《山西建筑》
2013年第23期191-192,共2页
Shanxi Architecture
关键词
贯通测量
误差
全站仪
三角高程
through measurement
error
total station meter