顶管遇障碍物处理技术

Technological Measures for Pipe Tacking When Meeting with Barriers
下载PDF
导出
摘要 随着经济的发展,建筑业在不断发展。在施工条件限制下,顶管技术在工程中应用越来越多。而顶管在掘进过程中,遇障碍物常是不可避免的。现通过南沙区某电厂顶管技术的应用,总结顶管遇障碍物的处理技术,供借鉴。 With the economic development of economy and the continuous expanding of building industry, the pipe jacking technology is applied more and more widely in the engineering projects in the case of limits by construction conditions. It is usually unavoidable to meet with barriers in the tunneling of pipe jacking. As a result of the application of pipe tacking in the certainn power plant in Nansha Section, the technological measures for pipe tacking when meeting with barriers are summarized for reference.
作者 赖丹云 谢伟
出处 《城市建筑》 2013年第2期97-97,共1页 Urbanism and Architecture
关键词 顶管 遇障碍物 处理技术 高压旋喷桩 压密注浆 pipe jacking meet with barriers technological measures high pressure jet grouting pile pressure grouting
  • 相关文献

参考文献2

  • 1余彬泉,等.顶管施工技术[M].人民交通出版社,2003.
  • 2余桂生.顶管施工中应注意的几个问题[J].广东省项管科研会,2004.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部