深圳地铁9号线工程风险防控研究

Case Study on Prevention and Control of Risks of Line 9 of Shenzhen Metro
下载PDF
导出
摘要 地铁工程是百年工程,工程风险防控不仅关系到工程的安全建造,且关乎到投资的合理回报。采用系统分析研究方法,对深圳地铁9号线工程的市场风险、资源风险、工程风险、管理风险、资金风险、外部协作配套条件风险进行系统性分析,提出了工程组织管理措施及技术措施等工程风险防范措施,对重大地质灾害、危险边坡、重大管线改迁、交通疏解风险控制等重大风险进行了专项风险控制方案对策研究,相关研究成果可为国内其他轨道交通工程提供借鉴。 Metro works has 100year service life. The prevention and control of the risks of Metro works are not only concerned with the safe construction of the Metro works, but also are concerned with the economic efficiency of the in vestment. Six types of major risk sources of line 9 of Shenzhen Metro, i. e. , market risks, resources risks, engineering risks, management risks, capital risks and coordination risks, are analyzed by means of system analysis method. Coun termeasures are proposed for engineering risks, geological disaster risks, dangerous slope risks, utility line re locating risks and traffic jam risks.
作者 赵德刚
出处 《隧道建设》 2013年第7期552-556,共5页 Tunnel Construction
关键词 地铁 工程风险 市场风险 资源风险 管理风险 资金风险 外部协作配套条件风险 防控对策 Metro engineering risk market risk resource risk management risk capital risk coordination risk countermeasure
  • 相关文献

参考文献14

二级参考文献108

共引文献184

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部