JNX70-2型焦炉烘炉实践

Practice of JNX70-2 Coke Oven
下载PDF
导出
摘要 焦炉投产前必须进行烘炉,而烘炉质量的好坏对焦炉的寿命至关重要。如何保证烘炉质量,是广大焦化工作者一直不断探讨的问题。在7 m焦炉从冷态转为正常加热的过程中,按照制定的升温计划,加强对火道的温度管理,使升温速率控制在允许的波动范围之内,同时通过定期测量炉体膨胀,加强对护炉铁件的调节,并及时对炉体裂缝进行修补,从而保证了焦炉的严密性,使新建焦炉从冷态平稳过渡到生产状态,为安全稳定生产奠定了基础。 The coke oven must be carried out before starting operation.The life of coke oven depends on the drying quality.How to guarantee the drying quality is the question workers have been discussed.In the process of 7 meters coke oven from cold state turning into normal heating state,it must be in accordance with the plan and strengthen the management of heating temperature.The furnace iron must be adjusted regularly by measuring the expansion of the furnace body,and timely repaired of furnace body crack,thereby the tightness of coke oven was ensured and the new coke oven was transited from cold state into production smoothly turning.This foundation for the safe and stable production in the future was laid.
作者 索小丽
出处 《煤炭与化工》 CAS 2013年第3期118-120,123,共4页 Coal and Chemical Industry
关键词 焦炉烘炉 升温曲线 温度管理 膨胀管理 coke oven temperature curve temperature management expansion management
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部