期刊文献+

泥水平衡式曲线顶管施工阶段技术研究 被引量:2

Slurry Balance Type Curve Pipe Jacking Construction Technology Research
下载PDF
导出
摘要 泥水平衡式顶管施工以其作业性能好、总顶力较小及施工进度快等优点受到顶管工程界的肯定,但其在施工过程中如果控制不当,将造成地面塌陷、污染环境及泥浆突涌等现象,特别是在曲线顶管测量控制不当的情况下问题更加突出。从泥浆配制、泥浆分离、曲线段测量及压密注浆技术四方面来探讨泥水平衡式曲线顶管施工阶段技术控制措施,为同类工程施工提供借鉴。 Type of slurry balance pipe j acking construction is sure by pipe j acking engineering with its good operating performance, small total jacking force, and the advantages of fast construction progress. However improper control in construction process will lead to ground subsidence, the phenomenon such as environmental pollution and slurry outburst flood, especially under the condition of the curve pipe jacking. This study discusses slurry balance type curve pipe jacking construction technology control measures in four aspects, such as slurry preparation, slurry separation, slurry curve segment measurement and pressure grouting technology, providing reference for the similar engineering construction.
作者 吴荣荣
出处 《工程建设与设计》 2013年第9期113-115,119,共4页 Construction & Design for Engineering
关键词 泥水平衡 顶管 曲线 施工技术 slurrybalance pipe jacking curve the construction teclmology
  • 相关文献

参考文献3

  • 1陈勇,陈永光,黄以华.长距离曲线顶管技术在电力管道工程中的应用[J].非开挖技术,2011(2):63-68. 被引量:6
  • 2中国非开挖技术协会.《顶管施工技术及验收规范》(试行)[s].北京:人民交通出版社,2006.
  • 3Zhang, Hao. Urban curvedjackingpipe construction surveycontrol[M]. Proceedings oft.he International Conference on Pipelines and Trenchless Technology2011.

共引文献5

同被引文献4

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...