广州地铁一号线公园前站目前是东南亚最大的地铁车站,车站交叉接点部分为三层五跨结构,其它部分为两层单跨结构,防水等级为一级,其地理位置重要,地质条件复杂,防水等级要求高。文章重点介绍了该站结构防水及渗漏水治理技术。
Gongyuanqian station of No. 1 line of Guangzhou metro, with a cross section of 'five spans in three levels ' in the intersection section and of ' single span in two levels' in the other sections, is the largest metro station in Southeast Asia at present. Due to the important location and complicated geology, the waterproofing standard of the station was designated to be the first class. The paper mainly describes the structure waterproofing and the treatment measures to leakage.