发电厂中合成气调压站及相关管道的吹扫及严密性试验不同于普通蒸汽管道的吹扫有其特殊要求,必须严格执行各项规程规范,此文对亲身制定和参加的整个过程进行论述。
Different with the common steam pipes, sweeping and leakage test of the synthesis gas regulatory station pipes should obey the special requirenlents. The corresponding regulations and standards should be seriously executed. In this paper, the sweeping and leakage test procedures are stated.
出处
《电力勘测设计》
2013年第4期41-46,共6页
Electric Power Survey & Design
关键词
合成气
管道吹扫
严密性试验
synthesis gas, pipe sweeping
leakage test.