基于资源时间因子的DSM项目群进度优化研究 被引量:6

Research on Program Schedule Optimization Based on DSM of Resource Time Factor
下载PDF
导出
摘要 在项目实践中,由于资源约束,从而会延长项目群的工期。为此,本文引入资源时间因子概念,采用设计结构矩阵(DSM),利用资源进入和退出时间因子矩阵描述了项目任务对资源的需求。提出了基于资源时间因子的遗传粒子群项目群进度优化方法。通过案例计算表明,该法可以有效缩短项目群工期,同时为项目决策者合理增加资源提供了新思路。 In the project practice, the project schedule would be prolonged due to resource constrained. Therefore, the paper first introduced a concept of resource time factor, adopts the design structure matrix(DSM) , then described the demand on resources according to program by using resources into time factors DSM and resources exit time factors DSM. Finally, the author presents a genetic particle swarm algorithm for program schedule optimization based on resource time factor. The calculation proves that the method not only can reduce the Program Schedule, but also can provide decision-makers with a new perspective in proper inereasing reasonable resources.
出处 《运筹与管理》 CSSCI CSCD 北大核心 2013年第4期93-100,共8页 Operations Research and Management Science
基金 上海市研究生教育创新计划资助 上海市重点学科建设资助项目(S30504)
关键词 项目管理 资源约束 资源时间因子 设计结构矩阵 进度优化 粒子群优化 project management resource constrained resource time factor design structure matrix scheduleoptimization particle swarm optimization (PSO)
  • 相关文献

参考文献11

  • 1Chen C H, Ling S F, Chen W. Project scheduling for collaborative product development using DSM[ J]. International Journal of Project Management, 2003, (21): 291-299.
  • 2Artigues C, Michelon P, Reusser S. Insertion techniques for static and dynamic resoure-constrained project scheduling[J]. European Journal of Operational Research, 2003, 149 (2) : 249-267.
  • 3Bouleimen K, Lecocq H. A new efficient simulated annealing algorithm for resource-constrained project scheduling problem and its multiple mode version[J]. European Journal of Operational Research, 2003, 149(2) : 268-281.
  • 4Ying Y, Shou Y Y, Li M. Hybrid genetic algorithm for resource constrained multi-project scheduling problem[ J]. Journal of Zhejiang University :Engineering Science, 2009, 43 (1) : 23-27.
  • 5Buddhakulsomsiri J, David S K. Priority rule-based heuristic for multi-mode resource constrained project scheduling problems with resources vacations and activity splitting[ J]. European Journal of Operational Research, 2007, 178 (2) : 374-390.
  • 6程序,吴澄.粒子群优化算法求解多模式项目再调度问题[J].计算机集成制造系统,2009,15(1):97-101. 被引量:17
  • 7Steward D V. The design structure system: a method for managing the design of complex systems[ J]. IEEE Trans Eng Man- age, 1981, 28(3) : 71-74.
  • 8Krishnan V, Eppinger S D, Whitney D E. A model-based framcwork to overlap product development activities[ J]. Manage- ment Science, 1997, 43(4) : 437-451.
  • 9Shi Y, Eberhart R C. A modified particle swarm optimizer[J]. Proceedings of IEEE International Conference on Evolutionary Computation, Anchorage, 1998. 69-73.
  • 10Angeline P J. Using selection to improve particle swarm optimization[ J]. Proceeding of the 1999 Congtess on Evolutionary Computation, Piscataway :IEEE Press, 1999. 84- 89.

二级参考文献13

  • 1李丹,张宏国.资源约束下多项目再调度算法[J].信息技术,2007,31(4):16-18. 被引量:5
  • 2HERROLEN W, REVCK B D E. Resource-constrained project scheduling: a survey of recent developments[J]. Computers & Operations Research, 1998, 25(4) :279- 302.
  • 3WEGLARZ J. Project scheduling: recent models, algorithms and applications [M]. Amsterdam, Netherlands:Kluwer, 1999.
  • 4ALAGOZ O, AZIZOGLU M. Rescheduling of identical parallel machines under machine eligibility constraints[J].European Journal of Operational Research, 2003, 149(1) :523-532.
  • 5SAKOUT H E, WALLACE M. Probe backtrack search for minimal perturbation in dynamic scheduling[J]. Constraints, 2000, 5(4) :359-388.
  • 6KAO H P, WANG B, DONG J, et al. An event-driven approach with makespan/cost tradeoff analysis for project portfolio scheduling [J]. Computers in Industry, 2006, 57 (5) 379-397.
  • 7SPRECHER A, DREXL A. Multi-mode resource-constrained project scheduling by a simple, general and powerful sequencing algorithm[J]. European Journal of Operational Research, 1998, 107(1) :431--450.
  • 8MIKA M, WALIGOR G, WEGLARZ J. Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models[J].European Journal of Operational Research, 2005, 164(1) :639-668.
  • 9KENNEDY J, EBERHART R C. Particle swarm optimization [C]//Proceedings of IEEE Conference on Neural Network. Piscataway, N.J. , USA:IEEE Press, 1995 : 1942-1948.
  • 10ZHANG H, LI X D, I.I H, et al. Particle swarm optimization-hased schemes for resource-constrained project scheduling[J]. Automation in Construction, 2005, 14(3) :393-404.

共引文献16

同被引文献65

引证文献6

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部