摘要
结合打拉亥站现状及作业情况,分析车站到发线的使用和园区内装车作业情况,提出车站存在的主要问题。从优化作业组织和站场设备改造2个角度,在合理使用到发线、组织列车均衡到达、压缩装车时间等优化作业组织的基础上进行打拉亥站站场改造,达到提高专用线的装车效率和车站运输组织能力的目的。
Combined with status and operation situation of Dalahai Station,this paper analyzes the use of station arrival-departure track and loading operation status inside the section,and puts forward main problems existing in station.From the views of optimizing operation organization and upgrading of station & yard facilities,Dalahai Station yard reconstruction was carried based on optimizing operation organization,such as reasonable use of arrival-departure track,organizing balanced arrival of trains and shortening loading time,so as to achieve the object of increasing loading efficiency of industrial line and capacity of station transport organization.
出处
《铁道货运》
2013年第8期26-29,5,共4页
Railway Freight Transport
关键词
铁路
打拉亥站
通过能力
扩能改造
Railway
Dalahai Station
Passing Capacity
Capacity Expansion and Reconstruction