摘要
谦比希铜矿深部上向分层水平充填采场顶板暴露面积较大,且上盘围岩节理裂隙发育,导致顶板垮冒严重,贫化问题突出。据此提出了采场顶板长锚索预锚固控顶技术,阐述了其支护机理、支护参数及施工工艺。实际应用表明:采用长锚索预锚固控顶、配合锚杆(钢带)联合支护,能够有效控制采场顶板冒落,为类似矿山提供了借鉴意义。
The room and pillar upward horizontal sublevel filling method is adopted in the deep ore body of Chambishi Copper Mine, the large exposed area of mine roof and developing joints of surrounding rock in the hanging wall led to serious roof collapse and ore dilution. Thus, the prestress anchorage technology with long anchor cable was put forward to control the stability of roof. The sup- port mechanism, parameter, and construetion process was introduced. Practice application shows that long anchor cable reinforcement technique can control effectively the collapse of mine roof in conjunction with the bolt and steel strip, which is a reference to similar mine.
出处
《铜业工程》
CAS
2013年第4期40-42,73,共4页
Copper Engineering
基金
国家"十二五"科技支撑计划项目(2012BAB08B02)
关键词
长锚索
预锚固
冒落机理
支护参数
施工工艺
long anchor cable
prestress anchorage
collapse mechanism
support parameter
construction process