摘要
从最易发生坍塌土层的确定以及泥浆槽壁稳定性分析这两个方面出发,对地下连续墙施工中泥浆的配比、施工过程等进行了研究,以设计出符合工程实际要求的泥浆,并应用到工程实际中,具有十分重要的意义。
From the identification for the soil layer subject to being collapsed and the stability analysis of mud cell walls, the paper has the study on the mud ratio and construction process of the underground continuous wall construction, so it is meaningful to design the mud adhering to the engineering demands and use it in projects.
出处
《山西建筑》
2013年第28期43-44,共2页
Shanxi Architecture
关键词
地下连续墙
施工
泥浆
设计
underground continuous wall, construction, mud, design