以朔州平鲁变电站新建工程为例,对地基处理设计采用的强夯处理法施工工艺进行了简要介绍,并阐述了其检测方法及工作量,分析了检测结果,最终得出了一些有意义的结论。
Taking the newly-built project of Pinglu transformer substation of Shuozhou as the example, the paper introduces the construction craft of the dynamic compaction method in the foundation treatment design, illustrates its test methods and workload, analyzes its test results, and a- chieves some beneficial conclusion.
出处
《山西建筑》
2013年第28期72-73,共2页
Shanxi Architecture
关键词
变电站
强夯法
检测
结果
substation, dynamic compaction method, test, result