摘要 双洎河渡槽为南水北调中线工程上的一座大型渡槽,采用双厢预应力矩形槽结构形式,利用造槽机施工。在设计过程中,用平面结构力学方法初步计算预应力筋配制,用三维有限元法进一步校核并优化槽身三向预应力布置。在槽身施工时,考虑到造槽机产生的施工期荷载,利用三维有限元法对槽身预应力筋提前张拉的顺序进行了优化。经上述设计优化,渡槽成功通过充水验证,证明了设计、施工的可靠性。 Shuangjihe pre - stressed thin - wall aqueduct with double box - sections, a large scale aqueduct in Middle Route Project of South - to - North Water Diversion, was build by aqueduct building machine. In the structure design process, layout of pre -stressed tendons were preliminarily analyzed by plain structural mechanics and further checked by 3D FEM. In aqueduct construction process, tensioning priority order of the pre - stressed tendons was optimized by 3D FEM considering construction temporary load induced by aqueduct building machine. Through the optimization, the aqueduct has passed the water - filling test, proving reliability of its design and construction.
出处 《人民长江》 北大核心 2013年第16期12-14,共3页 Yangtze River
基金 "十一五"国家科技支撑计划重大项目"南水北调工程若干关键技术研究与应用之大流量预应力渡槽设计和施工技术研究"(2006BAB04A05) 南水北调中线干线工程科技项目"大型预应力U形预制槽1:1原型试验和预应力张拉试验研究"(ZXJ/KY/YYL-001)
关键词 矩形渡槽 造槽机 施工荷载 张拉顺序 南水北调中线工程 rectangular aqueduct aqueduct building machine construction load tensioning priority order Middle Route Project of South - to - North Water Diversion
  • 相关文献

同被引文献41

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部