期刊文献+

塔式起重机在高炉热风炉炉壳吊装施工中的应用

APPLICATION OF TOWER CRANES IN THE HOISTING AND INSTALLATION OF HOT - BLAST FURNACE STOVE SHELLS
下载PDF
导出
摘要 介绍了安钢8#高炉4#热风炉的工程概况和施工难点。针对施工现场烟囱、皮带廊、介质管网等冶炼设施林立密集、场地异常拥挤,狭小区域内进行大体积炉壳吊装的特殊情况,制定了科学严谨的施工方案,采用M100-75型塔式起重机,将整个热风炉炉壳划分为十三吊进行吊装施工,不仅保证了施工质量和工期,而且大大降低了施工成本。 The paper introduce the project and difficulty in installation of NO. 4 hot stove for NO. 8 blast furnace. The No. M100 -75 tower crane, which divides the hoisting and installation of the whole shell into 13 times, is adopted to settle problems like over- crowded chimneys, belt corridors, medium networks and other smelting equipment at the construction site as well as hoisting and installing the shell in a limited space. In this way, the construction cost is greatly reduced while the project can still be completed at the scheduled time with quality ensured.
出处 《河南冶金》 2013年第4期50-53,共4页 Henan Metallurgy
关键词 塔式起重机 高炉热风炉 炉壳 吊装 tower crane hot - blast stove shell hoisting and installation
  • 相关文献

参考文献1

二级参考文献1

  • 1机械设计手册编写组.机械设计手册[M].北京:燃料化学工业出版社,1969..

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部