摘要
通过10 kV配电网运行方式调整优化区域电网容载比时,无法直观的看到调整后各变电所容载比的变化情况。利用海迅实时数据库开发了一个辅助软件,模拟运行方式调整,分析各变电所容载比的变化情况,为优化区域电网容载比提供依据,也为主变增容布点提供依据。
When adjusting and optimizing capacity-load ratio of regional power grid by means of operating mode of 10 kV distribution networks, it is unable to intuitively see the change of capacity-load ratio of sub- stations. With the help of HighSoon Real-time database, the aid software is developed to simulate the adjust- ment of operating mode and analyze the change of capacity-load ratio of substations, which provide basis for optimizing capacity-load ratio of regional power grid and location distribution for capacity increase of main transformers.
出处
《浙江电力》
2013年第9期57-59,共3页
Zhejiang Electric Power
关键词
海迅实时数据库
主变
容载比
优化
方式调整
HighSoon Real-time Database
main transformer
capacity-load ratio
optimization
mode ad-justment