摘要
对比某1×30 MW生物质电厂和目前国内同级别电厂,总结该项目主厂房布置的主要特点为:取消炉前中间料仓;汽机房0 m低位布置;锅炉房与主厂房并列布置。该项目主厂房的布置方案对类似规模生物质发电机组的设计有借鉴意义。
Comparing the main building arrangement of a 1 x 30 MW Biomass power plant with that of the same level plants in China, features of the main building arrangement are summarized as follows: the middle bunker in front of the furnace is removed, the steam turbine house is arranged at low position of 0m ; boiler house and main building are arranged in parallel. The arrangement scheme of the main building provides a reference for the design of biomass power plant of similar scale.
出处
《广西电力》
2013年第4期82-83,共2页
Guangxi Electric Power