摘要 为研究黄土基坑土钉支护结构中支护钉的工作性能,在某黄土基坑土钉支护现场选择1根试验钉进行拉拔试验,测试土钉受力后的内力分布及位移变化。试验结果表明,土钉在黄土基坑中有较好的工作性能,采用常规计算方法设计黄土工程中的土钉偏于保守。该试验对于改进黄土基坑土钉支护结构的设计方法具有一定的现实指导意义。 To study the working performance of soil nailing in loess foundation pit,pull-out test is carried out on one pilot soil nailing. The internal force distribution and the displacement varition of the soil nailing which has been loaded are studied. The result shows that the working performance of soil nailing in loess foundation pit is better, it is conservative to design soil nailing in loess foundation pit with the conventional calculation method. This test can be used to guide the design of soil nailing in loess foundation pit.
机构地区 青海大学
出处 《建筑科学》 北大核心 2013年第9期74-77,共4页 Building Science
基金 青海大学中青年科研基金项目(2011-QGT-1) 青海省科技厅应用基础研究计划项目(2012-Z-708)
关键词 黄土 基坑 土钉支护 工作性能 loess foundation pit soil nailing working performance
  • 相关文献

参考文献3

  • 1龚晓南 高有潮.深基坑工程设计施工手册[M].北京:中国建筑工业出版社,1999..
  • 2JGJ120-2012,建筑基坑支护技术规程[S].
  • 3CECS96:97.基坑土钉支护技术规程[S].[S].,..

共引文献402

同被引文献9

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部