摘要
抱箍法盖梁施工与满堂支架法、预留孔法等相比有施工操作简单、节省材料节省劳动力、周期短等明显的优势。抱箍法盖梁施工需要严密的计算,主要包括:侧模支撑计算、纵梁计算、抱箍计算。以郑州市K0+514主线上跨京广铁路分离式立交桥桥墩盖梁为例,验算盖梁施工中的抱箍应力是否达到施工要求。
As compared with full support method and reserved hole method, wrapping hoop method has obvious advantages, such as simple construction operation, material-saving, labor-saving and short cycle etc. The construction of a coping by embracing hoop method needs close calculations, mainly including: the calculation of side formwork support, calculation of longitudinal beam and that of wrapping hoop. Taking the pier coping of the separation overpass on Zhengzhou K0 + 514 line crossing the Beijing- Guangzhou Railway for example, the wrapping hoop stress was checked during construction of the coping, if it could meet the construction requirements.