以新疆哈密三塘湖风电场为例,介绍了整个工程的基本情况,分析了二、三、四期风机基础的优化过程。优化后节约了混凝土用量,节省了工程投资。
Taking Santanghu Wing Farm in Hami Xinjiang as example,the general information of the whole project was introduced. The optimization process of the wind turbine foundation design for project phase Ⅱ,phase Ⅲ and phase Ⅳ was analyzed. The used amount of the concrete was decreased due to the optimization,and the project investment was reduced.
出处
《华电技术》
CAS
2013年第9期70-72,79,共3页
HUADIAN TECHNOLOGY
关键词
风机基础
地震力
运行荷载
优化设计
wind turbine foundation
earthquake force
operational load