对工序开工期进行控制的“拟关键路径”法 被引量:5

Quasi-Critical Path Method for Controlling the Start-Time of Activity
下载PDF
导出
摘要 应用网络方法中“关键路径”的思想,定义了网络计划的“拟关键路径”.借助于工序的“拟关键度”,以最少总压缩时间为优化准则,讨论了含强迫时限工序的网络计划的时间优化问题,提出了可行的启发式算法。进一步给出了可在微机上实现的简单算法及计算机处理流程图。 A new idea of Quasi-Critical Path has been defined in terms of the thought of Critical Path for the network method. The paper studies the time control problem of a network with forced start-time activity by both the optimal criterion of minimal reduced time and the concept of Quasi-Critical Degree of activity, and proposes a realizable heuristic algorithm. Another simpler algorithm is also presented, which can be realized in microcomputer.
作者 胡汉辉
出处 《东南大学学报(自然科学版)》 EI CAS CSCD 1991年第3期38-43,共6页 Journal of Southeast University:Natural Science Edition
关键词 工序 开工 网络方法 拟关键路径 industrial engineering, network method, heuristic approach / Quasi-Critical Path, Quasi-Critical Degree of activity
  • 相关文献

参考文献6

  • 1胡汉辉,1988年
  • 2官世--,线性规划及其在建筑管理中的应用,1988年
  • 3江景波,建筑施工组织学,1987年
  • 4吴根生,统筹与科学管理,1983年,2期,46页
  • 5冯允成,系统工程理论与实践,1983年,4期,49页
  • 6江景波,网络计划的计算与实例,1983年

同被引文献16

引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部