摘要
针对宝钢不锈钢220 kV总降站监控系统运行中存在的问题,提出了监控系统改造的目标,并分析了改造的可行性及存在的难点问题,制定相应的解决方案,成功实现了该监控系统的升级改造,大大提高了该监控系统的稳定性及可靠性。
The goal of the upgrading project for the monitoring system of the 220 kV general step-down transformer substation at Baosteel Stainless Steel was put forward aiming at the existing problems in operation of the system. The feasibility and difficult issues of the revamping project were also analyzed and relevant solutions drawn up. As a result the moni- toring system was successfully upgraded, significantly improving the stability and reliability of the system.
出处
《冶金动力》
2013年第10期57-59,共3页
Metallurgical Power
关键词
总降站
监控系统
升级改造
general step-down transformer substation
monitoring system