期刊文献+

漕河渡槽灌注桩承载力与静载试验比较 被引量:2

Comparison of Design Bearing Capacity and Site Static Load Test of the Cast-in-place Piles in Caohe Aqueduct
下载PDF
导出
摘要 漕河渡槽槽身段采用灌注桩基础,桩基进入弱风化岩石0.5m,按纯端承桩计算桩基承载力。采用桩基静载试验检测桩基承载力,试验结果表明,漕河渡槽桩基承载力达到设计要求。 The cast-in-place piles foundation is adopted in the Caohe aqueduct body. There is 0.5 meter of the piles foun- dation entering into the weak weathered rock, the bearing capacity of the piles foundation is calculated according to point bearing pile. The static load test is adopted to check the the beating capacity of the cast-in-place pile foundation, the test results show that the beating capacity of pile foundation in Caohe aqueduct meet the design requirements.
作者 杨胜慧
出处 《水科学与工程技术》 2013年第5期28-30,共3页 Water Sciences and Engineering Technology
关键词 渡槽 灌注桩 承载力 沉降 桩基静载 aqueduct cast-in-place pile bearing capacity subside static load of pile foundation
  • 相关文献

参考文献6

二级参考文献4

共引文献470

同被引文献4

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部