高地应力区大直径TBM掘进岩爆风险控制 被引量:16

ROCKBURST RISK CONTROL FOR LARGE DIAMETER TBM BORING IN HIGH GEOSTRESS REGION
下载PDF
导出
摘要 锦屏二级水电站1#,3#引水隧洞采用TBM掘进,中部深埋洞段岩爆风险突出。为制定合理可行的掘进方案与岩爆防治措施,在前人研究基础上,结合工程实际情况,采用多种数值分析手段,评价不同形式导洞开掘,对降低岩爆风险的影响。3种导洞开挖方式均可以显著地降低TBM掘进的岩爆风险,选择何种形式的导洞主要从设备和经济效益角度进行决策。据此提出高地应力区大直径TBM掘进岩爆风险控制措施,施工中结合钻爆法导洞预处理、应力解除爆破并辅以及时、系统、高质量的支护,降低岩爆风险,确保施工及结构安全。 Water diversion tunnels #1 and #3 of Jinping II hydropower station are bored by tunnel boring machine(TBM). The rockburst risk is high in the middle alignment. For the purpose of establishing reasonable boring scheme and rockburst control measurement,based on previous researches,different numerical methods are used to evaluate different pilot boring schemes′ effects on reducing the rockburst risk,combining with actual situation. All these three pilot boring schemes can obviously reduce the rockburst risk. The selection of pilot boring schemes depends on the equipment and economic benefit factors. So,rockburst risk control measurements for large diameter TBM boring in high stress region are proposed. During TBM boring,the measurements of pilot,stress relieving blasting,assisting timely,systemic and high quality support are applied to reduce rockburst risk and ensure construction and structure safety.
出处 《岩石力学与工程学报》 EI CAS CSCD 北大核心 2013年第10期2100-2107,共8页 Chinese Journal of Rock Mechanics and Engineering
基金 国家自然科学基金资助项目(51109221 51079144)
关键词 岩石力学 深埋引水隧洞 强岩爆洞段 TBM施工 岩爆防治 导洞开挖 rock mechanics deep water diversion tunnel intense rockburst tunnel sections TBM boring rockburst control pilot boring
  • 相关文献

参考文献14

二级参考文献92

共引文献298

同被引文献186

引证文献16

二级引证文献247

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部