摘要
南塔河1号水电站径流设计时,由于该流域无长系列实测水文资料,坝址径流采用水文比拟法以临近南康河流域Ban Mixay水文站资料推求,并收集大量资料,从流域面积、降雨量、设计径流深等多方面着手,分析论证径流设计成果的合理性。
Due to lack of long series hydrological data in Nam Tha river basin,the damsite runoffs of Nam Tha #1 hy-dropower station were deduced through hydrologic analogy method according to the runoff data obtained from the near-by Ban Mixay hydrologic station in Nan Khan river basin. The rationality of the runoff design results was analyzed and demonstrated based on lots of collected data from several aspects such as basin area,rainfall,runoff dept etc.
出处
《红水河》
2013年第5期9-12,共4页
Hongshui River