摘要
通过工程实例提出动态方法研究隧洞穿过活动断裂的防震抗震问题,首先通过地表探槽和钻探初步判断活动断裂与隧洞相交的宏观位置;第二根据开挖揭露的断层性状,确定最新活动断裂的出露桩号;第三再通过施工地质编录资料研究抗震防震方案。
The paper proposes a dynamic method to study the earthquake-preparedness and earthquake-resistance problems byproject cases.The method hao three phases,the rirst phase is determination of the intersection location of active fault and tunnel by using trial trench and borehole;the second phase is determination of the stake number of the active fault by the characteristics revealed by excavation;the third phase is determination of the scheme of earthquake-preparedness adn esrthquake-resistance by construction geological logging.
出处
《资源环境与工程》
2013年第4期394-397,共4页
Resources Environment & Engineering
关键词
隧洞
活动断裂
抗震防震
动态方法
tunnel
active rault'earthquake-preparedness adn earthquake-resistance
dynamic method