摘要
阐述了软土地区预应力管桩在系杆拱桥箱梁支架基础中的应用。重点讲述了软土地区系杆拱桥箱梁支架及基础的施工流程、操作要点以及取得的效益。实践证明,在软土地区系杆拱桥箱梁支架基础施工中,用预应力管桩取代钻孔灌注桩或钢管桩,施工速度快,没有泥浆污染,成本降低,具有非常明显的经济与社会效益。
The application of pre-stressed pipe pile in tied arch bridge box gird- er support foundation in soft soil area was described. The construction process flow and the operation points of the tied arch bridge box girder support and foundation in soft soil area and the obtained benefits were introduced in detail. Practice shows that, during the construction of the support and foundation, pre-stressed pipe pile has been used to replace the cast-in-situ bored pile or steel pipe pile with quick construction speed, no slurry pollution, lower cost and remarkable economic and social benefits.
出处
《工程建设》
2013年第5期34-37,共4页
Engineering Construction
关键词
软土地区
预应力管桩
系杆拱桥
箱梁支架基础
施工
soft soil area
pre-stressed pipe pile
tied arch bridge
box girdersupport foundation
construction