江口水电站帷幕线深层特大溶洞处理措施 被引量:3

Treatment Measures for Ultra Large Cave Under Deep Curtain Line,Jiangkou Hydropower Project
下载PDF
导出
摘要 根据江口水电站右岸6号坝段及灌浆平洞RA、RB单元深层溶洞的地质特征,并结合防渗帷幕设计标准要求,依据实际施工条件,经过分析对比,确定了处理措施,通过施工验证和成果分析对比,认为灌注水泥砂浆、水泥-水玻璃、水泥-膨润土浆液处理溶洞的方法正确,过程控制得当,施工参数合理,效果显著,具有实用性。 In accordance with the geological conditions of the deep caves under Dam Section 6 and Unit RA and RB of the grouting adit on right bank of Jiangkou Hydropower Project as well as in combination with the specifications for design of the grouting curtain and the actual construction conditions, the treatment measures are finalized through analysis and comparison. The measures for treatment of the eaves by placement of cement mortar, cement-sodium silicate and cement-bentonite are proved proper through construction experience, result analysis and comparison. The treatment process is controlled properly, the construction parameters are reasonable and the treatment result is as exoected. Therefore. those treatment methods ft^r caw~ ~r,~ ,,ra^tio^l
出处 《西北水电》 2013年第5期16-20,共5页 Northwest Hydropower
关键词 帷幕线 特大溶洞 处理方法 江口水电站 curtain line ultra large cave treatment method Jiangkou Hydropower Project
  • 相关文献

参考文献7

  • 1水利电力部水利电力建设总局.水利水电施工组织设计手册[M].北京:中国水利水电出版社,1987.
  • 2DL/T5148-2001,水工建筑物水泥灌浆施工技术规范[S].北京:中国电力出版社,2008.
  • 3DL/T5200-2004,水电水利工程高压喷射灌浆技术规范[S].北京:中国电力出版社,2009.
  • 4DIMT5331-2005,水利水电工程钻孔压水试验规程[S].北京:中国建筑标准设计研究院,2006.
  • 5田金钢,张永保,孙江生.弓上水库采用高压喷射灌浆处理坝基深层渗漏[J].河南水利与南水北调,1999,28(2):41-41. 被引量:1
  • 6禹建强.毕节地区岩溶坝基渗漏及灌浆处理[A].工程地质勘察学术交流会论文选集[C].1994.
  • 7邹成杰.国内外岩溶地区水库坝址防渗帷幕设计中工程地质问题的综述与分析[J].水利水电技术,1987,(1).

共引文献3

同被引文献13

引证文献3

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部