通过城市道路面积和单位面积撒布量确定了项目的规模,介绍了项目的工艺操作流程和车间的具体布置情况。针对干式分装和湿式灌装的特点分别进行了具体的工艺设计和设备选型。
First determining the size of the project by the city road area and the amount of the scattereding for every unit area; and then introduced the project operation process and the layout of the workshop; Finally, giving the specific process designing and the selection of equipments for the dry and wet filling work.
出处
《工程建设与设计》
2013年第11期60-63,共4页
Construction & Design for Engineering
关键词
融雪剂
搅拌站
工艺设计
deicing salt
mixing station
process designing