摘要
通过对北京南枢纽列控系统集成工程中应答器报文及临时限速系统设计的分析,总结研究CTCS-2/CTCS-3等级线路接入CTCS-3D等级线路时需要注意的特殊点,对今后类似工程的列控系统设计提出建设性的意见。
Through the analysis of the design of the balise telegram and TSR system in the integrated project of the train control system for BeiJing south station as a junction station, the paper summarizes and studie specially considered points for connecting CTCS-2/CTCS-3 lines to CTCS-3D line, and puts forward the constructive opinions on the train control system design of similar projects in the future.
出处
《铁路通信信号工程技术》
2013年第5期11-15,共5页
Railway Signalling & Communication Engineering