酉水大桥引桥T梁制、架和主桥悬灌同时施工的工艺研究 被引量:1

Youshui Bridge T Beam,Frame and Main Bridge Cantilever Construction at the Same Time Process Research
下载PDF
导出
摘要 以湖南省张花高速酉水河大桥4×40+80+145+80 m预应力混凝土连续T梁和斜高墩大跨径预应力混凝土连续梁桥桥为工程背景,引桥40 m T梁和主桥18个悬臂节块同时施工,引桥40 m T梁制、架先于主桥完工,根据酉水大桥4#交接墩墩身高度达57 m、直线段长度为6.5 m及直线段混凝土方量为106.85 m3等特点,在架设完成的40 m T梁上布置贝雷片吊架作为施工4#交接墩边跨直线段的主要施工设备,直线段施工完成后边跨进行合龙,简述吊架构造,介绍边跨现浇段吊架施工工艺和边跨合龙张拉等关键工序,对同类桥梁加快工程施工进度和节约投资有重要指导意义。 taking Hunan Province Zhang Hua high-speed Youshui River Bridge 4 × 40 + 80 + 145+ 80 m prestressed concrete continuous T beam and the oblique pier and long-span prestressed concrete continuous beam Qiao Qiao as engineering background,the bridge 40 m T beam and the 18 cantilever segmental construction at the same time,the approach of 40 mT beam,frame before the main bridge is completed,according to the 4# handover Youshui bridge pier the height is 57 m,length is 6.5 m and line segment concrete side volume 106.85 m3 characteristics,main construction equipment layout Bailey bracket used as construction of 4# transfer pier side span straight line segments in 40 m T beam erection on the completion of construction,line segment after cross of closure,the suspension bracket structure,the side span cast-in-place section of pylon construction technology and side span closure tensioning key processes,to the similar bridge to speed up the construction progress and has an important significance in saving investment.
出处 《公路工程》 北大核心 2013年第5期188-192,共5页 Highway Engineering
关键词 主桥 引桥 同时施工 交接墩 边跨现浇段 吊架 边跨合龙 张拉 the main bridge construction at the same time transfer pier side span hanger side span closure Zhang La
  • 相关文献

参考文献3

  • 1GB50017-2003.钢结构设计规范[S].[S].,..
  • 2钢结构设计手册编委会.钢结构设计手册(第三版)[M].北京:中国建筑出版社,2008.
  • 3JTGD60-2004.公路桥涵设计通用规范[S].[S].,..

共引文献3596

同被引文献2

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部