基于多目标遗传算法的维修保障资源调度优化研究 被引量:5

Research on Maintenance Support Resources Optimization Based on Multi-objective Genetic Algorithm
下载PDF
导出
摘要 以某型特种车辆为研究对象,其三级保养工艺流程优化属于多目标资源受限项目调度问题(Multi-Objective RCPSP,MORCPSP),根据车辆维修保养实际调度特点和决策者关心最大完工时间、人力资源总负荷和关键人力资源负荷的3个优化目标,设计了一种基于工序和人力资源的双重编码方案,并针对双重编码进行了遗传操作算子的改进,采用了NSGA-II算法精英保留策略和快速非支配排序构造Pareto最优解集,针对某型车辆三级保养工艺流程问题,算法可以有效求得其17个最优解,最后采用加权法对求得的Pareto最优解进行评定。 This articles aims to research a type of special vehicle so as to optimize its technological process in "three--level" maintenance, which belongs to the issue of multi--objective resource constrained project scheduling problem (Multi -- Objective RCPSP, MORCPSP). It puts forward a dual coding scheme based on processes and human resources, according to the actual scheduling of maintenance and three opti- mization objective, makespan, human resources overall load and the key human resource to load, that policymakers concerned. We improved the genetic operator and dual coding, adopted the elite reserved strategy and fast non--dominated sort of NSGA--II to construct the Pareto optimal solution set. The case application validates the correctness of the multi--objective algorithm to solve the maintenance support.
出处 《计算机测量与控制》 北大核心 2013年第11期3017-3020,共4页 Computer Measurement &Control
关键词 维修保障 多目标优化 遗传算法 maintenance support multi--objective optimization genetic algorithm
  • 相关文献

参考文献5

二级参考文献30

  • 1张晓菲,张火明.精英策略的改进非支配遗传算法[J].中国计量学院学报,2010,21(1):52-58. 被引量:11
  • 2张超勇,饶运清,刘向军,李培根.基于POX交叉的遗传算法求解Job-Shop调度问题[J].中国机械工程,2004,15(23):2149-2153. 被引量:113
  • 3康波,陈光■,吕炳朝.基于混沌遗传算法的故障测试集最小化方法[J].仪器仪表学报,2005,26(1):100-103. 被引量:8
  • 4赵强.改进的混沌优化方法及其应用[J].自动化与仪器仪表,2006(3):90-92. 被引量:11
  • 5[1]Mo¨hring R H. Minimizing costs of resource requirements in project networks subject to a fixed completion time[J]. Operations Research, 1984, 32: 89-120.
  • 6[2]Bandelloni M, Tucci M, Rinaldi R. Optimal resource levelling using non-serial dynamic programming[J]. European Journal of Operational Research, 1994, 78: 162-177.
  • 7[3]Younis M A, Saad B. Optimal resource levelling of multi-resource projects[J]. Computers and Industrial Engineering, 1996, 31: 1-4.
  • 8[4]Leachman R C. Multiple resource levelling in construction systems through variation of activity intensities[J]. Naval Research Logistics Quarterly, 1983, 30: 187-198.
  • 9[5]Seibert J E, Evans G W. Time-constrained resource levelling[J]. Journal of Construction Engineering and Management, 1991, 117: 503-520.
  • 10[6]Demeulemeester E. Minimizing resource availability costs in time-limited project networks[J]. Management Science, 1995, 41(10): 1590-1598.

共引文献17

同被引文献48

引证文献5

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部