桂平航运枢纽坝前左岸防洪堤抗滑桩开挖过程中遇到岩溶、岩基破碎等不利因素的影响。施工过程中 ,采用了帷幕灌浆、埋管灌浆等措施 ,解决了涌水、渗漏问题 。
Some unfavorable factor such as carst and breaking batholite are encountered during the antislide pile excavation of flood protection dike on the left bank in front of the dam of Guiping navigation junction For the smooth construction of the project, measures such as curtain grouting and embedded pipe grouting are taken to solve the problems of surging and leaking
出处
《广西电力工程》
2000年第4期48-49,共2页
Guangxi Electric Power Engineering
关键词
防洪堤
除险加固
挖孔灌注桩
岩溶
帷幕灌浆
埋管灌浆
flood protection dike
strengthening
caisson pile by excavation,carst
curtain grouting
embedded pipe grouting