摘要
某建筑物由于河道开挖造成建筑物产生不均匀沉降倾斜 ,采用顶升纠偏法使建筑物纠正、复位 。
The building was settled and inclined seriously due to the nearby river bound excavation.Jacking up is adopted to rectify it and anchor-static-pushed piles are used to prevent the building from continuing settlement.
出处
《福建建筑》
2000年第B11期58-59,共2页
Fujian Architecture & Construction
关键词
顶升纠编
地基加固
建筑物
不均匀沉降
Rectifying inclined building by jacking up Foundation Reinforcement