三联隧道围岩大变形原因分析及处治措施 被引量:6

Cause Analysis and Treatment Measures for Large Deformation of the Rock Surrounding Sanlian Tunnel
下载PDF
导出
摘要 贵昆铁路六沾复线三联隧道施工中,在玄武岩与煤系地层不整合接触带附近发生围岩大变形。结合地质勘察、施工揭示、施工支护衬砌及开裂变形特征,全面分析围岩地质环境、地层工程特性,结构受力特性及施工方法、技术措施的适应性,找出支护结构变形的原因,并在隧道开挖过程中进行进一步的试验,从而提出针对性工程处治措施,实施后效果良好。 In construction of Sanlian Tunnel on Liupanshui-Zhanyi Double Line of Guiyang-Kuiming Railway, large deformations of surrounding rock arose nearby the unconformable contact zone between basalt and coal measure strata. Combining with geological survey, construction revelation, construction support and lining, and cracking and deforming behavior, the followings, including the geological environment of the surrounding rock, the engineering character of strata, the mechanical characteristics of the structure, and the adaptability of the construction method and technical measures were comprehensively analyzed, so as to find out the cause of deformation of the supporting structure. In addition, tests were made further in excavation of the tunnel. As a result, targeted engineering treatment measures were proposed and got good effect after implementation.
出处 《路基工程》 2013年第6期182-186,共5页 Subgrade Engineering
关键词 隧道 大变形 原因 措施 tunnel large deformations cause measures
  • 相关文献

参考文献4

  • 1TB10012 - 2007, J124 - 2007铁路工程地质勘察规范[S].北京:中国铁道出版社,2007.
  • 2TB10038 -2012, J1408 - 2012铁路工程特殊岩土勘察规程[S].北京:中国铁道出版社,2012.
  • 3TB10003--2005,J449--2005铁路隧道设计规范[S].北京:中国铁道出版社,2005.
  • 4铁道部第一勘察设计院.铁路工程地质手册[K].北京:中国铁道出版社,2005.

共引文献1

同被引文献77

引证文献6

二级引证文献74

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部