文中分析了竖井施工方案决策网络的特点,决策工程间的关系,0—1规划解法数学模型的建立过程,以及用树图的求解方法.
In this paper, the method for selectting optimal shaft construction plan is introduced by using the mathematical model of the 0-1 programming and minimum tree theory, and the table-cal-culation method for solving the model is introduced too.
关键词
坚进口
施工
最优方案
选择
main interlock engineering
minimum-tree
0-1 programming
method decision engineering
decision variable