IT项目进度计划风险量化预测方法 被引量:1

Quantification Prediction Method of Production Developement Schedule Risk
下载PDF
导出
摘要 针对IT项目进度基线定义质量普遍偏低的问题,提出了一种资源约束条件下基于蒙特卡洛模拟的进度风险量化评估方法.首先,考虑资源对进度的限制问题,提出资源约束条件下的活动历时抽样方法;其次,提出在活动历时随机变化情况下,项目关键路径动态识别方法,研究项目工期概率分布问题.最后,通过实例表明,资源约束条件下的蒙特卡洛模拟方法,能够有效地评估IT项目中的进度风险,辅助项目决策. Given the generally low quality of Production Development schedule baseline aetmltlOn, an eva^uauon method of project schedule risk quantification based on Monte Carlo simulation under the conditions of resource constraints is proposed. Firstly, considering the resource constraints on the progress, an activity duration sampling method under resource constraints is proposed. Secondly, to study the probability distribution of project duration, a method to recognize the critical path to a project dynamically is proposed under the random change in the activity duration. Finally, examples will show that Monte Carlo simulation methods under resource constraints can assess the progress risk of IT project effectively and support the project decision-making.
出处 《计算机系统应用》 2013年第12期13-18,38,共7页 Computer Systems & Applications
基金 内蒙古自然科学基金(2010MS1011)
关键词 资源约束 蒙特卡洛模拟 IT项目进度 风险量化评估 resource constraints Monte Carlo simulation production developement schedule QRA(quantitative riskevaluation)
  • 相关文献

参考文献10

二级参考文献49

共引文献167

同被引文献6

引证文献1

二级引证文献12

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部