FIDIC环境保护条款在国际工程项目中的应用研究 被引量:5

Application Study of FIDIC " Conditions of Contract for EPC / Turnkey Projects" in the International Engineering Project
下载PDF
导出
摘要 研究目的:FIDIC《设计采购施工(EPC)/交钥匙工程合同条件》是国际工程领域得到普遍公认和广泛应用的标准合同条件,其中的环境保护条款是制约项目成败的瓶颈之一,本文结合几内亚西芒杜矿山铁路项目实际,针对环境保护条款展开应用研究,为我国企业有效地处理好国际工程项目中有关环境保护条款的问题、进而顺利拓展国际工程领域项目提供合理建议。研究结论:(1)FIDIC《设计采购施工(EPC)/交钥匙工程合同条件》中环境保护条款对合同环境的依赖性很强,需全面深入研究履行合同区域的有关环保法律及规则;(2)环境保护需开始实施于项目设计阶段,坚持环保选线理念,为项目的环境保护建立可持续体系;(3)环境保护的具体措施落实在项目施工和运营阶段。 Research purposes: FIDIC "Conditions of Contract for EPC/Tumkey Projects" is the standard conditions of contract with universally recognized and widely used in international engineering field and the provision of environmental protection is one of most important provisions for the success of project. This paper researches on the provision of environmental protection basing on the project of Guinea Simandou rail, and provides reasonable proposals which are about effectively deal with the problems related to the provision of environmental protection in international projects and the smooth execution of international engineering project for Chinese enterprises. Research conclusions: ( 1 ) The provision of environmental protection of FIDIC " Conditions of Contract for EPC/Turnkey Projects" is so strong depending on contract environmental that we need to comprehensively and deeply study the relevant environmental protection laws and regulations in the area of performance of the contract. (2) Environmental protection needs to be early implemented in the course of project design stage and the design concept of environmental protection aligement should be complied with so as to build sustainable system for environmental protection of the project. (3) The specific measures for the environmental protection should be implemented in the course of project construction and operation stages.
作者 杨长根
出处 《铁道工程学报》 EI 北大核心 2013年第12期104-107,共4页 Journal of Railway Engineering Society
关键词 FIDIC《设计采购施工(EPC) 交钥匙工程合同条件》 环境保护 环保选线 环境影响 措施 设计阶段 施工阶段 营运阶段 FIDIC " Conditions of Contract for EPC/Turnkey Projects" environmental protection environmental protection aligement environmental influence measures design stage construction stage operation stage
  • 相关文献

参考文献9

二级参考文献26

共引文献109

同被引文献19

  • 1杨军,陈鹏万,胡刚.现代爆破技术[M].北京:北京理工大学出版社,2005:17-22.
  • 2肖汉甫,吴立,陈刚,等.实用爆破技术[M].武汉:中国地质大学出版社,2009.
  • 3夏彦.设计采购施工(EPC)总承包项目费用控制方法探讨[J].城市建设理论研究(电子版),2012,25(23):11-13.
  • 4李欣.对当前设计采购施工总承包(EPC模式-Engineering Procurement Constraction)工作的探索[J].城市建设理论研究(电子版),2013,45(24):11-12.
  • 5陈香宏.国际工程合同管理实践与菲迪克施工合同条件案例解析[D].北京:清华大学,2008.
  • 6任尚卿,程飞,张锦亮,等.DL/T5135-2001水利水电工程爆破施工技术规范[S].
  • 7陈跃熙,施富强,王其贵,等.GB50201-2012土方与爆破工程施工及验收规范[S].
  • 8QCS2010卡塔尔建设标准[S].
  • 9张宏升.工程爆破技术[M].北京:煤炭工业出版社,2011:15-18.
  • 10汪旭光,徐天瑞,张正宇,等.GB6722-2003爆破安全规程[S].

引证文献5

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部