摘要
当年完工投入使用的采暖管道,可以直接采用水压试验,而对完工后当年不投入运行的采暖管道,则应考虑气压试验,次年再对补做水压试验。
When the completion heating pipeline is put into use in that very year, can be directly used hydraulic pressure test, and the completed did not put into use heating pipeline immediately, should consider the pressure test, and the following year to do pressure test.
出处
《城市建筑》
2013年第20期311-311,共1页
Urbanism and Architecture
关键词
冬季
寒冷期
采暖管道
气压试验
winter, the cold period, heating pipes, pressure test