330MW氢冷发电机氢气置换耗时计算 被引量:1

330 MW Hydrogen-cooled Generator Hydrogen Replacement Time-consuming Calculation
下载PDF
导出
摘要 针对电厂氢冷发电机氢气置换操作所需时间都长短不一且差别很大的现状,以华能济宁运河电厂330MW氢冷发电机为例,分充氢、升氢压、排氢等三个阶段阐述一种氢冷发电机氢气置换耗时计算方法,可以有效指导电厂对氢冷发电机氢气置换的实际操作,减少安全隐患。 Aiming at the present situation of hydrogen replacement time for hydrogen-cooled generator in power plant is unconfirmed,and the difference is very big,taking 330 MW hydrogen cooled generator in Jining Canal Power Plant as an example,elaborates a kind of hydrogen-cooled generator hydrogen replacement time-consuming calculation method.According to the time consuming can effectively guide the actual operation of hydrogen-cooled generator hydrogen replacement,reduce the hidden danger.
出处 《山东电力技术》 2013年第6期70-73,共4页 Shandong Electric Power
关键词 330 MW氢冷发电机 氢气置换 耗时计算 管路 流速 330 MW hydrogen-cooled generator hydrogen replacement time-consuming calculation piping velocity
  • 相关文献

参考文献3

  • 1沈维道,童钧耕.工程热力学(第4版)[M].北京:高等教育出版社.2007.
  • 2GB50177--2005,氢气站设计规范[S].
  • 3火力发电职业技能培训教材编委会.电气设备运行[M].北京:中国电力出版社.2004.

共引文献4

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部