梨园水电站岸边式厂房布置紧凑合理,主机间与安装间不同高度布置、节省了投资;通过厂房三维有限元的分析研究,验证了厂房结构的安全性,确定了合适的蜗壳弹性垫层铺设范围;主厂房施工期先浇上、下游边墙方案加快了施工进度,保证了项目发电目标顺利实现。
The layout of the bank powerhouse of the Liyuan Hydropower Plant is compact and reasonable, and the main machine hall and the erection bay are arranged at different elevations, which reduces the investment outlay~ The three--dimensional finite element analysis and study of the powerhouse verified the safety of the powerhouse structure and determined the suitable laying extent of the spiral case elastic cushiota The scheduling of concreting the upstream and the downstream side walls first in construction of the main powerhouse sped up its construction, and thus successfully achieved the goal of power generation of the project.