摘要
清水河中、下游段水能资源理论蕴藏量16.32 MW,其中,中游河段水能理论蕴藏量约为9.25 MW,占56.7%;下游河段水能理论蕴藏量为7.06 MW,占43.3%。依据水头及实际地形条件,中游河段布置两级电站。此梯级位于拟建伯斯阿木水库坝址下游直线距离约3.5 km处,根据1/5万地形图分析,采用引水式开发布置,建发电引水隧洞。参考已建并运行多年的若羌河梯级电站,针对清水河中、下游水能开发利用进行探索。
The theory hydropower resources reserves is 16.32MW at the middle and downstream section of the Qingshui River, in which middle section is 9. 25 MW, accounting for 56%, and downstream section is7.06MW, accounting for 43.3%. According to the water head and topographical conditions two stages hydropower stations are arranged in the middle section. The statin is located3.5km away from the planned dam site of Bosi'amu reservoir straightly downstream, water diversion type is adopted for the station and diversion tunnel will be buih. Taking the existing Ruoqing reference,which has operated for years, the hydropower development downstream section of Qingshui River. staged hydropower station as a is studied for the middle and
出处
《黑龙江水利科技》
2013年第10期35-37,共3页
Heilongjiang Hydraulic Science and Technology
关键词
水能利用
梯级电站
引水式
开发规划
清水河
hydropower utilization
staged hydropower station
water diversion type
developmentplanning
Qingshui River